The TCISD Bond Election passed overwhelmingly on November 6, 2007.
Progress Summary as of September 15, 2009
Projects in Construction
New Texas City High School
Approved Design Concept
Construction Start - 08/01/2009
Construction Finish - 10/27/2011
Heights Elementary School
Construction Start - 06/16/2009
Construction Finish - 06/10/2010
Northside Elementary School
Construction Start - 06/16/2009
Construction Finish - 08/05/2010
Roosevelt-Wilson Elementary School
Construction Start - 06/22/2009
Construction Finish - 06/10/2010
Simpson Education Support Center
Construction Start - 11/01/2009
Construction Finish - 08/31/2010
Projects in Design
Stingaree Stadium Renovations
Completion of Design - 08/01/2009
Project Bid - 08/16/2009 to 09/16/2009
Construction Start - 01/01/2010
Construction Finish - 04/01/2010
Projects Completed
Athletic Project - Synthetic Turf at Stadium
Completed Turf
Construction Start - 06/02/2008
Construction Finish - 09/14/2008
New Franz Kohfeldt Elementary School
Photo of Completed School
Construction Start - 06/10/2008
Construction Finish - 08/14/2009
New Levi Fry Intermediate School
Photo of Completed School
Construction Start - 06/10/2008
Construction Finish - 08/14/2009
Northside Elementary School Drives & Parking
Construction Start - 02/11/2009
Construction Finish - 06/15/2009
Abatement and Demolition at old Kohfeldt, old Levi Fry and old TCHS pool
Construction Start - 06/15/2009
Construction Finish - 09/03/2009